Companies/Oracle/infrastructure
scalinginfrastructure

Stargate and OpenAI capacity

The 4.5 GW Oracle–OpenAI plan was announced in July 2025. Bloomberg reported in March 2026 that the Abilene expansion was dropped; Oracle called those reports false and incorrect.

ORCL market data

The numbers

Additional Stargate data center capacity agreed with Oracle (planned)4.5 GWAnnounced July 22, 2025 · source ↗

What it is

Oracle builds and runs AI data centers for OpenAI under the Stargate programme, including the Abilene, Texas site. Oracle has not disclosed the megawatts or GPU counts per site, so capacity is tracked from press reports and the company's own statements.

Why it matters to the stock. Much of the RPO increase is tied to OpenAI-linked capacity. Any change to the Stargate schedule or size changes the revenue path the stock is priced on.

News

Oracle weighs trucked natural gas for Project Jupiter as pipeline delays bite; shares fall about 5.5%

Bloomberg reported on October 8, 2026 that Oracle is considering trucking compressed natural gas to the 2.45 GW Project Jupiter campus in New Mexico, because the gas pipeline is delayed.

Project

WSJ report that OpenAI missed targets pushes Oracle down 4% to $166

A Wall Street Journal report said OpenAI missed its goal of one billion weekly ChatGPT users by the end of 2025 and fell short of several 2026 monthly revenue targets.

News

$16 billion Saline Township data center for Oracle secures financing

Related Digital and Blackstone-affiliated funds announced financing for a $16 billion data center campus in Saline Township, Michigan, built for Oracle.

Capital

Bloomberg reports 600 MW Abilene expansion for OpenAI dropped

Bloomberg reported on March 9, 2026, citing people familiar with the project, that plans for up to 600 MW of extra capacity near the Abilene, Texas Stargate site were dropped.

News