Nebius commits about £1.7B to three new UK AI sites totalling 65 MW
Nebius said it is committing about £1.7 billion to build out capacity at four UK sites, including three new NVIDIA-based deployments that together reach 65 MW when fully ramped in 2027. The release did not name the sites. The expansion adds UK capacity to the build-out that drives the 5 GW contracted-power target for year-end 2026.
- Investment: approximately £1.7 billion
- Three new NVIDIA-based deployments totalling 65 MW when fully ramped
- Full ramp expected in 2027
- Sites were not named in the release
NBIS around the story · hourly24 h reaction ▼ 9.42%
Source
Nebius newsroomJun 8, 2026